POWER PROJECTS - SUBSTATION PROJECTS

INSTALLING EQUIPMENT ON GAS POWER PLANT AZURA EDO 330kV SS, BENIN

  • Client: Siemens Nigeria Ltd.
  • Location: Benin, Nigeria
  • Project status: Completed 2017

Project characteristics:

Installing equipment on a new gas power plant Azura, also on existing substation Benin North and construction of 3 linking 330kV towers. Equipment is Siemens AG.

INSTALLING EQUIPMENT ON GAS POWER PLANT AZURA EDO 330kV SS, BENIN

CONSTRUCTION OF SUBSTATION UGWUAJI (EXTENSION) 330/132/33kV, 1x150MVA & 1x60MVA

  • Client: NDPHC / NIPP & Federal Ministry of Power & Steel
  • Location: Ugwuaji, Nigeria
  • Project status: Completed 2015

Project characteristics:

Turn key EPC project – Design, supply, construction & commissioning of 1x150MVA, 330/132kV and 1x60MVA, 132/33kV substation.

CONSTRUCTION OF SUBSTATION UGWUAJI (EXTENSION) 330/132/33kV, 1x150MVA & 1x60MVA

SUBSTATION UGWUAJI 330kV (SWITCHYARD)

  • Client: NDPHC / NIPP & Federal Ministry of Power and Steel
  • Location: Ugwuaji, Nigeria
  • Project status: Completed 2014

Project characteristics:

Turn key EPC project – Design, supply, construction & commissioning of 330kV Substation (Switchyard) Ugwuaji.

SUBSTATION UGWUAJI 330kV (SWITCHYARD)

SUBSTATION OKE ARO (ERUKAN)

  • Client: Federal Ministry of Power and Steel & NDPHC / NIPP
  • Location: Lagos, Lagos state, Nigeria
  • Project status: Completed 2013

Project characteristics:

Turn key EPC project - Design, procurement, construction & commissioning of substation.
2x300MVA 330/132kV, 1 1/5 CBS per bay, 3 OHL diameter, 1 trafo-diameter, 2x300MVA autotransformers, 330/132/33kV and 1x75MVA, 330kV shunt reactor.
2x60MVA 132/33kV, 1 1/5 CBS per bay, 5 OHL diameter, 2 trafo-diameter, 2x60MVA power transformer 132/33kV and 6x33kV OHL Bays.

SUBSTATION OKE ARO (ERUKAN)

330kV SUBSTATION AT GAS TURBINE POWER PLANT – GEREGU II Geregu, Lokoja, Kogi State, Nigeria

  • Client: Siemens Limited (Nigeria)
  • Location: Lokoja, Kogi State, Nigeria
  • Project status: Completed 2013

Project characteristics:

Erection, Installation & Commissioning of 330kV Substation at Gas Turbine Power Plant.

330kV SUBSTATION AT GAS TURBINE POWER PLANT – GEREGU II Geregu, Lokoja, Kogi State, Nigeria

REPLACEMENT OF DISTANCE PROTECTION RELAYS

  • Client: NEPA
  • Location: Nigeria
  • Project status: Completed 2005

Project characteristics:

Replacement of distance protection relays in 11 Grid power plants and substations in various country areas.

REPLACEMENT OF DISTANCE PROTECTION RELAYS

SUBSTATION „KATAMPE“

  • Client: NEPA
  • Location: Abuja, Nigeria
  • Project status: Completed 2003

Project characteristics:

Design, procurement, construction & commissioning of 2x150MVA, 330/132kV and 2x60MVA, 132/33kV SG with double bus-bars and 1 1/2 CBS. Connection to new 330kV and existing 132kV transmission line. Construction of residential houses for operational and maintenance staff.

SUBSTATION „KATAMPE“

SUBSTATION „CENTRAL AREA“ (GIS)

  • Client: NEPA
  • Location: Abuja, Nigeria
  • Project status: Completed 2004

Project characteristics:

Design, procurement, construction & commissioning of GIS substation, 2x60MVA, 132/33kV SG with double bus-bars and 1 1/2 CBS. Construction of residential houses for operational and maintenance staff.

SUBSTATION „CENTRAL AREA“ (GIS)

SUBSTATION UYO

  • Client: NEPA
  • Location: Akwa Ibom State, Nigeria
  • Project status: Completed 1997

Project characteristics:

As the main contractor, Energo has successfully completed project of the Sub Station Uyo on the Turn Key basis.

Design, procurement, construction and commissioning of 2x40MVA, 132/33kV SG with connection to the existing 132kV SC Transmission Line. Construction of three residential houses for the Client’s operation and maintenance staff.

SUBSTATION UYO

SUBSTATION ILESHA

  • Client: NEPA
  • Location: Ilesha - Osun State, Nigeria
  • Project status: Completed 1998

Project characteristics:

Energo executed Turn Key project as the subcontractor of ABB for the following works: Design, procurement, construction and commissioning of the Ilesha Substation.

Standard NEPA Substation, 2x40MVA, 132/33kV with connection to the existing 132 kV SC Transmission line. Construction of residential houses for operational and maintenance staff.

SUBSTATION ILESHA

POWER PROJECTS - TRANSMISSION AND DISTRIBUTION

CCECC - Relocation of 132kV & 330kV Lines for Kaduna-Kano Railway

  • Client: CCECC
  • Location: Kaduna-Kano
  • Project status: Ongoing
  • Construction period: 2023

Project characteristics:

Relocation of 132kV & 330kV Transmission lines, Towers and Conductor.

CCECC - Relocation of 132kV & 330kV Lines for Kaduna-Kano Railway

Transmission Line from Ihovbor GPP Substation to 330kV TL Benin - Ajaokuta, Benin, Nigeria

  • Client: Transmission Company of Nigeria Plc. (TCN)
  • Location: Benin - Ajaokuta, Nigeria
  • Project status: Ongoing

Project characteristics:

Engineering, Procurement and Construction of 330kV SC Over Head Transmission Line from Ihovbor GPP Substation to 330kV TL Benin - Ajaokuta

Transmission Line from Ihovbor GPP Substation to 330kV TL Benin - Ajaokuta, Benin, Nigeria

Transmission Lines within Abuja - Abuja Power Ring - LOT 2, Abuja, Nigeria

  • Client: Transmission Company of Nigeria Plc. (TCN)
  • Location: Abuja - Abuja Power Ring
  • Project status: Ongoing

Project characteristics:

Engineering, Procurement and Construction of 132kV DC Overhead Transmission Line within Abuja - Abuja Power Ring - LOT 2

Transmission Lines within Abuja - Abuja Power Ring - LOT 2, Abuja, Nigeria

Transmission Line Abuja - Lafia - Abuja Power Ring - LOT 1, Abuja, Nigeria

  • Client: Transmission Company of Nigeria Plc. (TCN)
  • Location: Abuja - Lafia
  • Project status: Ongoing

Project characteristics:

Engineering, Procurement and Construction of 330kV DC Overhead Transmission Line Abuja - Lafia - Abuja Power Ring - LOT 1

Transmission Line Abuja - Lafia - Abuja Power Ring - LOT 1, Abuja, Nigeria

CONSTRUCTION OF 132kV SC TRANSMISSION LINE AND 132/33/3.3kV SUBSTATION at “Tarkwa” Island – Lagos for Atlas Cove Oil Depot

  • Client: Nigerian National Petroleum Corporation (NNPC)
  • Location: “Tarkwa” Island – Lagos
  • Project status: Completed 2016

Project characteristics:

Turn key EPC project –Design, supply, construction & commissioning of 132kV SC Transmission Line 20km long and 1x15MVA & 2x7.5MVA, 132/33/3.3kV Substation.

CONSTRUCTION OF 132kV SC TRANSMISSION LINE AND 132/33/3.3kV SUBSTATION at “Tarkwa” Island – Lagos for Atlas Cove Oil Depot

TRANSMISSION LINE ERUKAN – OMOTOSHO

  • Client: Transmission Company of Nigeria (TCN)
  • Location: Erukan – Omotosho, Nigeria
  • Project status: Ongoing

Project characteristics:

Turn key project – Design, supply, construction & commissioning of 330kV DC Over Head
Transmission Line – 160km.

TRANSMISSION LINE ERUKAN – OMOTOSHO

TRANSMISSION LINE UGWUAJI – IKOT EKPENE

  • Client: Niger Delta Power Holding Company (NDPHC) / NIPP
  • Location: Enugu and Akwa Ibom States, Nigeria
  • Project status: Completed 2015

Project characteristics:

Turn key EPC project - Design, supply, construction and commissioning of two DC 330kV Transmission Lines, 2x162km + 7km long, conductor type - twin bundle ACSR “BISON”, steel latice towers, from Ugwuaji to Ikot Ekpene and Ugwuaji to New Haven (7km).
Construction of 330kV SG in New Haven.

TRANSMISSION LINE UGWUAJI – IKOT EKPENE

TRANSMISSION LINE KATAMPE - NATIONAL STADIUM, ABUJA

  • Client: Power Holding Company of Nigerian (PHCN)
  • Location: Abuja, Nigeria
  • Project status: Completed 2016

Project characteristics:

Turn key project – Design, supply, construction & commissioning of 132kV DC combine Cable/OHTL connection - 12 km.

TRANSMISSION LINE KATAMPE - NATIONAL STADIUM, ABUJA

REHABILITATION AND EXPANSION OF ABUJA AIRPORT EXPRESSWAY - DUALIZATION OF STREET LIGHTING

  • Client: Bilfinger Berger AG Nigeria Division & Julius Berger Nigeria PLC / Federal Capital Development Authority (FCDA)
  • Location: Abuja, Nigeria
  • Project status: Completed 2013

Project characteristics:

Electrical Works, Procurement, Installation, Testing and Commissioning.
LOCATION: Airport Expressway Abuja - Gwagvalada.
SYSTEMS: Street Lighting System and associated accessories (excluding poles), 10 No. Transformers 500kVA, 33kV/0.415kV compact substations, underground cables and street lighting along 44km airport highway Abuja.

REHABILITATION AND EXPANSION OF ABUJA AIRPORT EXPRESSWAY - DUALIZATION OF STREET LIGHTING

LEKKI - IKOYI BRIDGE, LAGOS

  • Client: Bilfinger Berger AG Nigeria Division & Julius Berger Nigeria PLC
  • Location: Lagos, Nigeria
  • Project status: Completed 2013

Project characteristics:

Electrical Works, Procurement and Delivery (CPT Bremen), Installation, Testing and Commissioning.
Electrical Systems: Street Lighting, Toll Station, Pylon - Obstruction Lighting and Decorative Illumination.

LEKKI - IKOYI BRIDGE, LAGOS

TRANSMISSION LINE JOS – KAFANCHAN

  • Client: Power Holding Company of Nigeria (PHCN)
  • Location: Plateau and Kaduna States, Nigeria
  • Project status: Completed 2012

Project characteristics:

Turn key EPC project - Engineering, procurement and construction of 132kV DC Transmission Line, 80km long.
Conductor type - twin bundle ACSR “BEAR”, steel latice towers, average span 200m.

TRANSMISSION LINE JOS – KAFANCHAN

REHABILITATION OF 132kV DC TRANSMISSION LINE KADUNA - ZARIA

  • Client: Power Holding Company of Nigerian (PHCN)
  • Location: Kaduna - Zaria, Nigeria
  • Project status: Completed 2011

Project characteristics:

Rehabilitation of 80 km 132kV Transmission Line. First instalment of T-ACSR conductor in Nigeria.

REHABILITATION OF 132kV DC TRANSMISSION LINE KADUNA - ZARIA

TRANSMISSION LINE 132kV DC, AFAM – PORT HARCOURT

  • Client: Taleveras Group / Saipem / Rivers State Government
  • Location: Afam – Eleme (Port Harcourt), Nigeria
  • Project status: Completed 2011

Project characteristics:

Turn key project – Design, supply, construction & commissioning of 26km 132kV DC Over Head Transmission Line.

TRANSMISSION LINE 132kV DC, AFAM – PORT HARCOURT

PORT HARCOURT ELME JUNCTION – STREET LIGHTING

  • Client: Bilfinger Berger AG Nigeria Division & Julius Berger Nigeria PLC
  • Location: Lagos, Nigeria
  • Project status: Completed 2011

Project characteristics:

Electrical works, procurement and delivery (FOB Bremen), installation, testing and commissioning.
SYSTEM: Street Lighting System and associated accessories (109 poles) including Transformer 500kVA.

PORT HARCOURT ELME JUNCTION – STREET LIGHTING

TRANSMISSION LINE EGBIN – BENIN / EGBIN IKEJA WEST & SUBSTATION EGBIN EXTENTION

  • Client: Power Holding Company of Nigeria (PHCN)
  • Location: Lagos State, Nigeria
  • Project status: Completed 2009

Project characteristics:

Design, procurement, construction & commissioning of 330kV DC transmission line 28km long, conductor type – twin bundle ACSR “BISON”, steel lattice towers, average span 400m.
Design, procurement, construction & commissioning of 2 additional line bays in 330/132kV substation at Egbin.

TRANSMISSION LINE EGBIN – BENIN / EGBIN IKEJA WEST & SUBSTATION EGBIN EXTENTION

DISTRIBUTION LINE 33kV DC, APO SUBSTATION – ABUJA INTERNATIONAL AIRPORT

  • Client: NDPHC / Federal Ministry of Power and Steel
  • Location: Abuja, Nigeria
  • Project status: Completed 2008

Project characteristics:

Turn key project – Construction of 33kV DC distribution line, 44km from Apo Substation to Abuja International Airport.

DISTRIBUTION LINE 33kV DC, APO SUBSTATION – ABUJA INTERNATIONAL AIRPORT

TRANSMISSION LINE SHIRORO – ABUJA

  • Client: Nigerian Electricity Power Authority (NEPA) / ABB
  • Location: Abuja State, Nigeria
  • Project status: Completed 2005

Project characteristics:

Construction of 330kV DC Transmission Line, 150km long, conductor type – twin bundle ACSR “BISON”, steel lattice towers, average span 400m.

TRANSMISSION LINE SHIRORO – ABUJA

TRANSMISSION LINE ALIADE –MAKURDI

  • Client: Nigerian Electricity Power Authority (NEPA)
  • Location: Benue State, Nigeria
  • Project status: Completed 2001

Project characteristics:

330kV SC Transmission Line, 46km long, conductors type ACSR “Bison” 350 mm2 two per phase, earth–wire conductor GSW 2x140mm2. Steel lattice self supported structure. Average span 400m.

TRANSMISSION LINE ALIADE –MAKURDI

DISTRIBUTION LINE AJA – LEKKI

  • Client: NEPA
  • Location: Lagos
  • Project status: Completed 2000

Project characteristics:

Energo executed on the Turn key basis procurement and construction of the distribution line with the following characteristics:

33kV DC Distribution Line, 20km long, conductor type – ACSR “Bear”, steel lattice towers and steel poles.

DISTRIBUTION LINE AJA – LEKKI

LDSE - LAGOS DISTRIBUTION SYSTEM

  • Client: Nigerian Electricity Power Authority (NEPA)
  • Location: Lagos State, Nigeria
  • Project status: Completed 1992

Project characteristics:

The project LDSE represents one of the most sophisticated expansion project of the network at different voltage levels. As such it takes an outstanding place among the ones executed by Energo Nigeria in the past.
99km 132kV DC Transmission Line and 50km 33kV DC Distribution Line. 488 steel lattice towers for 132kV and 516 tubular steel poles for 132kV and 33kV. Phase conductors – ACSR “Bear”, protection cable steel 58mm2, glass cap insulators and long porcelain insulators with safety clamps.

LDSE - LAGOS DISTRIBUTION SYSTEM

NEPA POWER SUPPLY TO CLN HOSPITAL AND RECREATION CENTER

  • Client: CHEVRON NIGERIA Ltd
  • Location: Oworonoshoki / Gbagada, Lagos Nigeria
  • Project status: Completed 1999

Project characteristics:

Project consisted of laying of 33kV underground cable network (cable type 3x150mm2 XLPE/SWA/PVC) between NEPA’s 132/33kV substation at Oworonshoki and 33/11kV, 2MVA substation at CLN at Agbada as well as all civil, electrical and mechanical works on the SS.

NEPA POWER SUPPLY TO CLN HOSPITAL AND RECREATION CENTER

TELECOMMUNICATION AND GSM PROJECTS

EXTENSION OF SCADA SIGNALS AT KATAMPE SUBSTATION

  • Client: Nigerian Electricity Power Authority (NEPA)
  • Location: Abuja, Nigeria
  • Project status: Completed 2007

Project characteristics:

Turn key project - Extension of SCADA signals from the switchyard to the control rooms at Katampe 132/33kV substation.

EXTENSION OF SCADA SIGNALS AT KATAMPE SUBSTATION

GSM REPETITOR STATIONS

  • Client: GLOBALCOM / SIEMENS
  • Location: Kaduna, Jos, Bauchi, Nigeria
  • Project status: Completed 2005

Project characteristics:

Project consisted of civil works (foundation, station...) and erection of new towers with antennas of 40 – 90m high on digital microwave link.

GSM REPETITOR STATIONS

GSM REPETITOR STATIONS

  • Client: NITEL / SIEMENS, NEPA / SIEMENS
  • Location: Jos-Makurdi, Kaduna-Kano, Abuja-Kaduna-Bauchi, Kuta-Shiroro, Nigeria
  • Project status: Completed 1999

Project characteristics:

Project consisted of refurbishment and erection of new towers with antennas 50-80m high on the digital microwave link.
In order to upgrade, modernize and digitalize the existing power supply of telecommunication network with solar panels, Energo, as a subcontractor of Nitel/Siemens, has performed: design, civil works on control buildings, supply and maintenance on refurbishment of the existing exchange network, erection installation and erection of new towers with antennas and solar panels on digital microwave links.

GSM REPETITOR STATIONS

WATER TREATMENT PROJECTS

NATIONAL WATER REHABILITATION PROJECT

  • Client: Plateau State Water Board
  • Location: Plateau State – Jos, Laminga, Yakubu Gowon, Bukuru
  • Project status: Completed 1997

Project characteristics:

National Rehabilitation Project of Plateau State - Supply and installation of water pumps, 450kVA generator, hydrochloride system and chlorination unit, overhaul and repair of two 530kVA Darman generators. Rehabilitation of some water supply systems in the State, including supply of water tanker, workshop equipment, jib crane, mobile laboratory kit and spare parts for the various mechanical and electrical systems.
Consultants: Water and Dam Service Company (WADCO) Nigeria, IBG Ltd. Switzerland

Treatment Plant: Laminga – Jos 20l/sec, Lafia, Yakubu Gowon 800l/sec, Bukuru raw water pumps – motor capacity 34KW, 1470 RPM, 56m/head.

NATIONAL WATER REHABILITATION PROJECT

MEP - BUILDING SERVICES PROJECTS

CONSTRUCTION OF MULTI-MODAL FACILITY, GE CALABAR - EMERALD

  • Client: General Electric / Julius Berger FZE
  • Location: Calabar (CFTZ), Nigeria
  • Project status: On going

Project characteristics:

Turn Key Project – MEP, design, engineering services, testing and commissioning.
Units: Multi - modal manufacturing facility, training & administration facility, energy center, gas storage, water reservoir, waste storage, etc.

CONSTRUCTION OF MULTI-MODAL FACILITY, GE CALABAR - EMERALD

CONSTRUCTION OF MULTI-MODAL FACILITY, GE CALABAR - EMERALD

NATIONAL INSTITUTE FOR LEGISLATIVE STUDIES, ABUJA

  • Client: Bilfinger Berger AG Nigeria Division & Julius Berger Nigeria PLC / Federal Government of Nigeria
  • Location: Abuja, Nigeria
  • Project status: On going

Project characteristics:

Turn Key Project - MEP (Mechanical, Plumbing & Electrical) works, Design and Engineering Services. Procurement, construction and commissioning of all mechanical, plumbing, fire fighting and MCC systems.
BUILDINGS: Convention Center, Library, Admin. Building, Lecture Theatre, Main Reception, Junior Staff Quarters, Clinic, Power House, Maintenance Building, Main Gate, Chiller Plant (~64,650 m2).

NATIONAL INSTITUTE FOR LEGISLATIVE STUDIES, ABUJA

NATIONAL INSTITUTE FOR LEGISLATIVE STUDIES, ABUJA

NATIONAL ASSEMBLY RESIDENCE COMPLEX, ABUJA

  • Client: Bilfinger Berger AG Nigeria Division & Julius Berger Nigeria PLC / Federal Government of Nigeria
  • Location: Abuja, Nigeria
  • Project status: On going

Project characteristics:

Turn Key Project - Engineering, Procurement, Construction and Commissioning of all infrastructure, MEP, Audio / Visual, Security and BMS Systems.
BUILDINGS: Compound Senate President, Compound Speaker of the House (HoR), Compound Deputy Senate President, Compound Deputy Speaker of the House (HoR), General Area / Infrastructure (~ 14,300 m2).

NATIONAL ASSEMBLY RESIDENCE COMPLEX, ABUJA

UYO STADIUM

  • Client: Bilfinger Berger AG Nigeria Division & Julius Berger Nigeria PLC / Akwa Ibom State Government
  • Location: Uyo, Nigeria
  • Project status: Completed 2014

Project characteristics:

MEP – Mechanical, Plumbing & Electrical Works, Procurement and Delivery (FOS Uyo), Installation, Testing and Commissioning.

Buildings: Main Stadium incl. Ticket Booth, Infrastructure, Generator House, Sewage Treatment Plant, Water Reservoir, Workshop, Diesel Gen sets / Switchgear, Gate House I & II, Training Pitch (~ 64,700 m2).
Sanitary and Fire Protection: Sewerage System, Storm Water Drainage, Water Supply – Hot & Cold, FF Extinguisher.
Mechanical: Diesel Oil Supply System.

ELV Systems: PABX, Public Address, Clock System, Audio-Video System, Multimedia, CATV, Fire alarm, CCTV.
Electrical LV: 3xGen-Sets 1500kVA + 1xGen-Sets 800kVA, UPS, Power supply cables and SDBs, Internal lighting system, Sports lighting, Decorative Luminaries, Dimming system, Earthing & Lightning.
Electrical Infrastructure: 4x11kV substations (switchgear and transformers), 4 x Main switchgear (MDB) 0,415kV, Street lighting, Decorative luminaries, Fire Alarm, CCTV cabling, Fiber optic cabling.

HVAC & Control System: CHW System with Fresh Air Supply, DX Units System, Ventilation, MCC.

Plumbing Infrastructure: Fire Fighting System, Irrigation System and Potable Water Supply System, WTP, Pump Stations – Fire Fighting & Potable & Irrigation, STP.

UYO STADIUM

UYO STADIUM

UYO STADIUM

UYO’S GOVERNMENT COMPLEX / PHASE I – Governors Lodge, PHASE II – Guest house with Gate Houses and Banquet Hall, PHASE III – Government Offices

  • Client: Bilfinger Berger, Germany & Julius Berger Nigeria PLC
  • Location: UYO, Nigeria
  • Project status: Completed 2013

Project characteristics:

The Project includes preparation of detailed and as build design, procurement of all the equipment and materials, construction, commissioning, training of client’s personnel and other post-construction services for the high and low voltage systems, HVAC systems, and mechanical (potable and waste water, drainage and fire fighting) systems.

ELECTRICAL:
Power supply, HV Equipment, LV Equipment, Power Installation, Lighting, Lightning and Earthing Protection, MCC & MCP.

HVAC:
Central A/C system consists of 6 air-cooled chillers for CHW, supply for 11 AHU’s, CHW pump station, Fan coil units system and DX Split Units system.

Fire Protection:
Fire Hydrant System and Argon Gas Extinguishing Systems.

Plumbing:
Water Supply, Sewerage System, Drainage.

BMS&EMCS:
Building Management System, Electrical Monitoring & Control System.

Telecommunication:
Telephony System, Data Network, Fire Detection, Burglar Alarm, Access Control, Cable TV, CCTV, Multimedia presentation, Public Address and Voice Alarm System.

UYO’S GOVERNMENT COMPLEX / PHASE I – Governors Lodge, PHASE II – Guest house with Gate Houses and Banquet Hall, PHASE III – Government Offices

UYO’S GOVERNMENT COMPLEX / PHASE I – Governors Lodge, PHASE II – Guest house with Gate Houses and Banquet Hall, PHASE III – Government Offices

UYO’S GOVERNMENT COMPLEX / PHASE I – Governors Lodge, PHASE II – Guest house with Gate Houses and Banquet Hall, PHASE III – Government Offices

NATIONAL ASSEMBLY COMPLEX, ABUJA, NIGERIA / Phase III Part 1 - House of Senate and House of Representative, Phase III Part 2 - Extension Senate Block and House of Representative

  • Client: Bilfinger Berger, Germany & Julius Berger Nigeria PLC
  • Location: Abuja, Nigeria
  • Project status: Completed 2011

Project characteristics:

The project consists of M&P (mechanical and plumbing) and fire protection systems services – including equipment procurement, installation, testing and commissioning. Area 75,000m2.

HVAC:
Central A/C system consists of 6 air-cooled chillers for CHW, supply for 11 AHU’s, CHW pump station, Fan coil units system and DX Split Units system. Fire Protection Fire Hydrant System and Argon Gas Extinguishing Systems.

Plumbing:
Water Supply, Sewerage System, Drainage.

MCC:
Motor Control Centers including protection and control for all HVAC and Fire protection systems.

NATIONAL ASSEMBLY COMPLEX, ABUJA, NIGERIA / Phase III Part 1 - House of Senate and House of Representative, Phase III Part 2 - Extension Senate Block and House of Representative

NATIONAL ASSEMBLY COMPLEX, ABUJA, NIGERIA / Phase III Part 1 - House of Senate and House of Representative, Phase III Part 2 - Extension Senate Block and House of Representative

BAT CIGARETTE FACTORY IBADAN

  • Client: BAT - British American Tobbaco
  • Location: Ibadan, Nigeria
  • Project status: Completed 2003

Project characteristics:

Cigarette Factory Project done for British American Tobacco, one of the World leading Companies in Tobacco Industry. Area 22000m2.

The Project consists of highest standard special customized MEP systems for this type of industrial buildings and includes detailed design, procurement, installation, testing and commissioning, training, as built documentation, operation & maintenance manuals, defect liability period.

HVAC:
Central A/C systems with 3 chillers with screw compressors, Air Handling Units, DX package Units, Fan Coil Units, Ventilation.

Fire Protection:
Sprinkler, Hydrant, Standpipe, Hose reels, Inergen (IG100), Foam Deluge.

Plumbing:
Water Treatment Plant, Water Supply, Waste Water Treatment Plant, Sewerage System, Drainage, Irrigation System.

BMS & EMCS:
Building Management System, Electrical Monitoring & Control System.

Technology installations:
Steam plant, Liquid Petroleum Gas Plant, Vacuum Plant, Compressed Air Plant, Fuel Oil Supply Plant, Fuel oil Supply Yard.

Telecommunication:
Telephony System, Data Network, Fire Detection, Burglar Alarm, Access Control,CCTV, Public Address and Voice Alarm System.

BAT CIGARETTE FACTORY IBADAN

BAT CIGARETTE FACTORY IBADAN

BAT CIGARETTE FACTORY IBADAN

BUILDINGS CONSTRUCTION PROJECTS

EMBASSY OF THE REPUBLIC OF SERBIA IN ABUJA, NIGERIA

  • Client: Energoprojekt / Government of the Republic of Serbia
  • Location: Abuja
  • Project status: Completed 2015

Project characteristics:

Turn key EPC project – Design, supply, construction & commissioning.

EMBASSY OF THE REPUBLIC OF SERBIA IN ABUJA, NIGERIA

TWIN LAKES REAL ESTATE DEVELOPMENT / Phase 1A, Phase 2

  • Client: Bilfinger Berger AG Nigeria Division & Julius Berger Nigeria PLC / Chevron
  • Location: Lagos, Nigeria
  • Project status: Completed 2013

Project characteristics:

MEP – Mechanical, plumbing & electrical works design, procurement, installation, testing & commissioning

Buildings:
Construction of various facilities for 12,000 residents: Telecom Building, Power Plant Building, Gate Houses 1 & 2, WTP, STP, Infrastructure.

Electrical and Technology installations: 15MVA, 33/11kV Transformer Substation, 11kV Panel Indoor,
11kV & 0.415kV Outdoor Equipment – RMU and Packaged Substation, SDBs, Outdoor Lighting,
Lighting Kiosk, 4 x 11kV, 2250kVA Gen-Sets. Control Panel, Packaged Substation, UPS, Internal lighting system.
Earthing & Lightning protection. Diesel Oil Supply System.
Telecommunication: Voice and Data, Fire alarm, CCTV.
HVAC: CHW System with Fresh Air Supply, Down Flow Close Control Unit, Package Condensing Unit, Ventilation.
Plumbing: Sewerage System, Water Drainage, Water supply.
Fire Protection: Sprinkler, Hose reels, FM 200, Portable fire fighting extinguisher.

TWIN LAKES REAL ESTATE DEVELOPMENT / Phase 1A, Phase 2

TWIN LAKES REAL ESTATE DEVELOPMENT / Phase 1A, Phase 2

PRIVATE VILLAS & COMPOUNDS

  • Client: Private investors
  • Location: Abuja and Lagos, Nigeria
  • Project status: Completed and on going

Project characteristics:

Projects on Turn key basis included design, material and equipment procurement, civil, electrical, mechanical and plumbing works of several private villas and compounds.
Area of the executed projects varied from a few hundred to few thousand square meters. Interior design was also designed and performed by our specialists in cooperation with local subcontractors.

PRIVATE VILLAS & COMPOUNDS