COMPLETED AND PROJECTS IN PROGRESS IN NIGERIA / AFRICA

 
Projects Client Contract Value Year of Completion Project Description
Construction of transformer substation 2x10MVA, 110/30kV, Gabiro, Rwanda Energy Development Corporation Limited (EDCL) 7,147,000 $ on going Plant design, supply, construction and commissioning
Construction of transformer substation 1x10MVA, 110/30kV, Ntendezi and extension of Bugarama tansformer substation, Rwanda Energy Development Corporation Limited (EDCL) 5,949,878 $ on going Plant design, supply and installation
Construction of Multi-modal facility, Free trade Zone Calabar, Nigeria General Electric / Julius Berger FZE 29,772,485 $ on going Turn key project
National Assembly Residence Complex (ANR) – Abuja, Nigeria Julius Berger Plc / Federal Government of Nigeria 18,350,000 $ on going Turn key project - Engineering, Procurement, Construction and Commissioning of all infrastructure, EMP, Audio/Visual, Security, BMS systems on the project
National Assembly Institute for Legislative Studies Complex (ANI – Abuja) – Abuja, Nigeria Julius Berger Plc / Federal Government of Nigeria 18,300,000 $ on going Turn Key Project – Engineering, Procurement, Construction and Commissioning of all Mechanical, plumbing, fire fighting and MCC systems on the projec
Private Villa & compound, Nigeria Rodnab Construction Ltd / Private Investor 9,750,000 $ on going Turn Key Project – Engineering, Procurement, Construction and Commissioning of all infrastructure, EMP, Audio/Visual, Security, BMS systems and power and water supply
Construction of Transformer Substation 1 x 150 MVA & 1 x 60 MVA 330/132/33kV, Ihiala, Nigeria NDPHC/Federal Ministry of Power & Steel 9,400,000 $ on going EPC project –Design, partial supply, construction & commissioning of 1 x 150MVA 330/132kV and 1 x 60MVA 132/33kV substation
132kV Double circuit Over Head Transmission Line Elelenw -Rukpokwu Port Harcourt, Rivers State, Nigeria Talaveras Group of Companies 3,900,000 $ on going Turn key EPC project –Design, supply, construction & commissioning of 18 km of DC Transmission Line
Construction of 132kV SC Transmission Line and 132/33/3.3kV Substation at “Tarkwa” Island – Lagos for Atlas Cove Oil Depot - NNPC Nigerian National Petroleum Corporation (NNPC) 11,500,000 $ on going Turn key EPC project –Design, supply, construction & commissioning of 20km of 132kV SC Transmission Line & 1x15MVA & 2x7.5MVA, 132/33/3.3kV Substation
Construction of 330 kV, DC Transmission Line (160 km), Erukan-Omotosho Transmission Company of Nigeria (TCN) 33,000,000 $ on going Turn key EPC project –Design, supply, construction & commissioning of 330kV DC Over Head Transmission Line – 160km
Construction of Transformer Substation 1 x 150 MVA & 1 x 60MVA, 330/132/33kV (extension), Ugwuaji, Nigeria NDPHC/Federal Ministry of Power & Steel 11,500,000 $ 2015 Turn key EPC project –Design, supply, construction & commissioning of 1 x 150MVA 330/132kV and 1 x 60MVA 132/33kV substation
Rehabilitation of collapsed 330kV Sapele – Aladja Transmission Line Transmission Company of Nigeria (TCN) 1,440,000 $ 2015 Removal of collapsed towers and material, procurement & supply of new towers and additional stringing material, construction & commissioning of rehabilitated OHTL
Construction of 132 kV Transmission Line – Gurara-Kudenda, Nigeria Salini Nigeria Ltd/ Federal Ministry of Water Resources 12,445,359 $ 2015 Turn key EPC project –Design, supply, construction & commissioning of 80 km of 132kV Transmission Line
Embassy of The Republic of Serbia in Abuja, Nigeria Energoprojekt/ Government of the Republic of Serbia 4,700,000 $ 2015 Turn key EPC project –Design, supply, construction & commissioning
Construction of 132kV, DC, Transmission Line: Underground HV Cable / OHTL Katampe -National Stadium, Abuja Transmission Company of Nigeria (TCN) 13,980,000 $ 2015 Turn key EPC project – Engineering, supply, construction & commissioning of 132kV DC combine Cable/OHTL connection - 12 km
Construction of two 330kV DC Transmission Lines (2x162km), Ugwuaji - Ikot Ekpene Niger Delta Power Holding Company (NDPHC/NIPP) 91,110,000 $ 2015 Turn key EPC project - Design, supply, construction and commissioning of 330kV DC Transmission Lines, (2 x 162 km) Ugwuaji - Ikot Ekpene
UYO Stadium Julius Berger PLC / Akwa Ibom State Government 18,300,000 $ 2014 Turn Key Project – Engineering, Procurement, Construction and Commissioning of all MEP, Audio/Visual, Security, BMS systems, power and water supply
330kV Substation (Switchyard) Ugwuaji and 330kV OHTL Ugwuaji - New Haven (7km), Nigeria NDPHC / Federal Ministry of Power and Steel 25,053,368 $ 2014 Turn key EPC project – Design, supply, construction & commissioning of 330kV Substation and 330kV DC OHTL Ugwuaji - New Haven
Twin Lakes Real Estate Development Phase 2, Lagos Julius Berger Plc / Chevron 6,250,000 $ 2013 Construction of various facilities for 12,000 residents (diesel-generator station, water treatment plants (potable and waste water, telecommunication systems etc.)
330kV Substation at Gas Turbine Power Plant – GEREGU II Geregu, Lokoja, Kogi State, Nigeria Siemens Limited (Nigeria) 1,100,000 $ 2013 Construction, Installation & Commissioning of 330kV Substation at Gas Turbine Power Plant
132kV Double circuit Over Head Transmission Line Afam – Trans Amadi Afam, Rivers State, Nigeria Talaveras Group of Companies 5,200,000 $ 2013 Turn key EPC project –Design, supply, construction & commissioning of 24 km of DC Transmission Line
Governors Lodge Uyo - Phase III, Uyo, Akwa Ibom State Julius Berger PLC / Akwa Ibom State Government 2,580,000 $ 2013 Design, supply, installation, testing and commissioning for Electrical, Mechanical, Fire-fighting and Plumbing systems (equipment, materials and services)
Construction of Transformer Substation Oke-Aro (Erukan), 2x300MVA, 330/132kV and 2x60MVA, 132/33kV, Lagos NDPHC/Federal Ministry of Power & Steel 30,777,370 $ 2013 Turn key EPC project – Engineering, procurement and construction of 2x300MVA 330/132kV and 2x60MVA 132/33kV SG
Dualization of street lighting, Abuja - Gwagvalada highway Julius Berger PLC /Federal Capital Development Authority (FCDA) 7,540,000 $ 2013 33kV/0.415kV compact substations, underground cables and street lighting along 44km airport highway Abuja - Gwagwalada
Street Lighting – New Lekki - Ikoyi Bridge - Lagos Julius Berger Plc / Lagos State Government 980,000 $ 2012 Street and decorative Bridge Lighting
Twin Lakes Real Estate Development Phase 1A, Lagos Julius Berger Plc / Chevron 11,590,000 $ 2012 Construction of various facilities for 12,000 residents (diesel-generator station, water treatment plants (potable and waste water, telecommunication systems etc.)
Governors Lodge Uyo, Phase II, Akwa Ibom State Julius Berger PLC / Akwa Ibom State Government 11,820,000 $ 2012 Design, supply, installation, testing and commissioning for Electrical, Mechanical, Fire-fighting and Plumbing systems (equipment, materials and services)
Construction of 132kV DC Transmission Line (80km), Jos – Kafanchan PHCN 10,160,000 $ 2012 Turn key EPC project – engineering, procurement and construction of 132kV DC Transmission Line
Reconstructions and relocations of Distribution and Transmission Lines, 33kV & 132KV in Abuja Salini Nigeria Ltd/ Julius Berger Plc / CCECC 1,020,000 $ 2012 Various reconstruction and diversions due to construction of roads and railways
Reconstructions of Transmission Lines, 132kV DC in Lagos CCECC/LAMATA 1,480,000 $ 2011 Various reconstruction and diversions due to construction of railway in Lagos
Transmission Line 132kV DC (26km), Afam – Port Harcourt Taleveras Group / Sypem/Rivers State Government 6,970,000 $ 2011 Turn key EPC project –Design, supply, construction & commissioning of 132kV DC Over Head Transmission Line Afam - Eleme (Port Harcourt)
National Assembly Complex Phase III, Part 2, Abuja Julius Berger PLC / Federal Government 6,902,000 $ 2011 Design, supply, installation, testing and commissioning for Mechanical (sanitary and HVAC) and Fire-fighting systems (equipment, materials and services)
Rehabilitation of 132kV DC Transmission Line Kaduna-Zaria PHCN 2,300,000 $ 2011 Rehabilitation of 80 km 132kV transmission line. First instalment of T-ACSR conductor in Nigeria.
Relocation of Distribution Line, 33kV DC, Apo substation – Abuja International Airport Julius Berger PLC / FCDA 2,000,000 $ 2011 Various reconstruction and diversions due to dualization of expressway
Governors Lodge Uyo, Phase I, Uyo, Akwa Ibom State Julius Berger PLC / Akwa Ibom State Government 8,556,800 $ 2009 Design, supply, installation, testing and commissioning for Electrical, Mechanical, Fire-fighting and Plumbing systems (equipment, materials and services)
Transmission Line 330kV DC, Egbin - Ikeja West / Benin, Lagos and Extension of 330/132kV substation at Egbin PHCN 9,700,000 $ 2009 Turn key EPC project - Design, procurement, construction & commissioning of 28km DC TL and 2 additional bays in 330/132kV substation at Egbin
Distribution Line, 33kV DC (44km), Apo substation – Abuja International Airport NDPHC/Federal Ministry of Power & Steel 4,500,000 $ 2008 Turn key project – construction of 33kV DC distribution line
Extension of SCADA signals from the switchyard to the control rooms at Katampe 132/33 kV substation NEPA 350,000 $ 2007 Turn key project
National Assembly Office Complex, Phase III, Part 1, Abuja Julius Berger PLC / Federal Government 11,000,000 $ 2007 Design, supply, installation, testing and commissioning for Mechanical (HVAC), Fire-fighting, Plumbing and MCC systems (equipment, materials and services)
Switchyard at Gas Turbine Power Plant at Geregu, Ajaokuta Siemens, Nigeria / Federal Government 750,000 $ 2006 Turn Key project - erection of switchyard 330kV at Gas Turbine Power Plant - Geregu
Transmission Line, 330 kV DC, Shiroro - Abuja NEPA/ABB 12,450,000 $ 2005 Erection of 144km, 330 kV DC overhead transmission line from Abuja to Shiroro
Electrification of 9 villages, Gombe state NEPA 450,000 $ 2005 Construction of 167km of 0.4; 10; 33kV rural electrification lines & substations
GSM Repeater Stations Kaduna - Jos Link Globalcom / Siemens 500,000 $ 2005 Civil works and antenna tower erection for 5 repeater stations
Power supply at Federated Steel Mills Factory, Otta, Ogun State FSM 1,240,000 $ 2005 Refurbishment and upgrading of2x20MVA, 33/11kV substation, 11kV UG Cable distribution and 11kV SWGR
Housing Development at Ologun Agbeje Rd., Victoria Island, Lagos Globalcom 4,100,000 $ 2005 Turn Key Project – Design, procurement, erection and commissioning of 4 floor residential building with flats for GLO
Replacement of Distance Protection Relays NEPA 3,020,000 $ 2005 Replacement of distance protection in 11 Grid Power Plants and substations; Nigeria
Construction of 132kV DC Transmission Line; Underground HV Cable/OHTL combine connection „Katampe“ –„Central Area“, Abuja NEPA 19,190,000 $ 2005 Design, supply, construction & commissioning of 132kV DC combine Cable/OHTL connection - 10 km
Substation „Central Area“, 2X60MVA, 132/33kV, Abuja NEPA 15,030,000 $ 2004 Design, supply, construction & commissioning of GIS Indoor Substations 2X60MVA, 132kV SG with double bus-bars and 1 1/2 CBs
Kwajaffa extension electrification project NEPA 260,000 $ 2004 Construction of 33kV rural electrification lines & substations
Substation „Katampe“, 2X60MVA, 132/33KV, Abuja NEPA 10,870,000 $ 2003 Design, supply, construction & commissioning of 2X60MVA, 132kV SG with double bus-bars and 1 1/2 CBS - 33kV OHTL bays
Substation „Katampe“, 2X150MVA, 330/132kV, Abuja NEPA 17,360,000 $ 2003 Design, supply, construction & commissioning of 2X150MVA, 330kV SG with double bus-bars and 1 1/2 CBS
Distribution Line, 33 kV DC line, Otta - FSM, Lagos NEPA 730,000 $ 2003 Design, supply, construction and commissioning of 3.46km long 33 kV DC distribution line
BAT, New Cigarette Factory Ibadan BAT / Energoprojekt Oprema 20,000,000 $ 2003 MEP services – procurement, installation of electrical and mechanical systems, plumbing and automation
Distribution Line 33 kV DC line, Lekki – Victoria Island, Lagos NEPA 460,000 $ 2003 Design, supply, construction & commissioning of 33kV DC distribution line - 2 km
Reinforcement of SS „Papalanto“ 132/33kV NEPA 370,000 $ 2002 Reinforcement of 132/33kV substation at Papalanto
Distribution Line, 33 kV Garkida-Biu-K.Kusar-Byriel, Borno state NEPA 1,800,000 $ 2002 Construction of 142 km of 33 kV rural electrification lines
Substation „Otta“, 2x45MVA, 132/33/11kV, Ogun State NEPA 1,620,000 $ 2001 Refurbishment of SS 2x45 MVA 132/33/11kV
Substation „Alausa“, 2x45MVA, 132/33/11kV, Lagos State NEPA 1,980,000 $ 2001 Refurbishment of SS 2x45 MVA 132/33 /11kV
Transmission Line, 330kV SC, Aliade - Makurdi NEPA 6,400,000 $ 2001 Construction of 46km, 330kV SC transmission line
Mobile Station , 30 MVA, 132/33kV, Makurdi NEPA 1,980,000 $ 2001 Turn Key project – Design, procurement, erection and commissioning of mobile station 30MVA, 132/33kV
Micro Wave Antenna towers at Abia, Zamfara & Gombe NITEL/Siemens 500,000 $ 2000 Dismantling and re-erection of 4 towers (2x120m, 85m & 50m)
Distribution line, 33kV DC, Aja Lekki - Lagos NEPA 5,700,000 $ 2000 Turn Key project – procurement and construction of 20 km, 33kV DC distribution line
Antenna towers on Kuta-Shiroko NITEL/Siemens 93,000 $ 1999 Erection of 3 towers
Repeater Stations, Kano-Kaduna NITEL/Siemens 311,765 $ 1999 Control Building Civil Works - 6 stations
Distribution line, 33kV DC, Amuwo-Satellite, Lagos NEPA 120,000 $ 1999 Construction of 33 kV D/C distribution line
Benin-Delta 330 kV TL rehabilitation NEPA 328,000 $ 1999 Re-erection of 11 collapsed towers of 132kV line
Distribution line Apir – Makurdi, 33kV, Benue State NEPA 1,440,000 $ 1999 Turn Key project –construction of 15km, 33kV DC distribution line
SS „Apir“, 1x15MVA, 132/33 kV, Makurdi, Benue state, NEPA 1,980,000 $ 1999 Turn Key project –construction of SS 132/33 kV, 1x15MVA
Substation „Ilesha“, 2x40MVA, 132/33kV, Osun State NEPA 2,170,000 $ 1998 Turn Key Project –Design, procurement, erection and commissioning of SS 2x40MVA, 132/33kV Ilesha
Access to hangars at Kaduna Airport Sky Power 360,000 $ 1998 Construction of access area 7200m2 to hangars at Kaduna airport
33kV underground cable Oworonshoki-Ogudu, Lagos NEPA 1,980,000 $ 1998 Laying of 33kV DC underground cable
Substation „Uyo“, 2x40MVA, 132/33kV, Akwa Ibom State NEPA 7,260,000 $ 1997 Turn Key project – Design, procurement, erection and commissioning of 2x40MVA, 132/33kV SG
National Water Rehabilitation Project, Plateau State Plateau State Water Board 1,000,000 $ 1997 Refurbishment and extension of water plants
Micro Wave Antennas Jos - Makurdi, Abuja-Kaduna-Bauchi NITEL/Siemens 170,000 $ 1997 Erection of 6 antennas, platforms & fastenings, re-erection of towers
Turning in and out of TL Itu-Eket at SS „Uyo“ NEPA 560,000 $ 1997 Construction of turning in & out of 132kV TL Itu – Eket at 132/33kV SS „Uyo“
Power Supply to CNL Hospital and Recreation Center, Lagos Chevron 370,000 $ 1997 Construction of power supply to CHL hospital and recreation center
Staffhousing at SNCC Shiroro dam NEPA 1,250,000 $ 1997 Construction of 18 bungalows, 52.000m2
Repeater Stations Jos- Makurdi NITEL/Siemens 1,762,000 $ 1996 Control Building Civil Works - 9 stations
Repetitor station Jos - Makurdi NITEL/Siemens 1,762,000 $ 1996 Refurbishment and erection of new towers with antennas 50-80m high on the digital microwave link - control building and 9 stations
Power supply system, Calabar NITEL/Siemens 1,762,000 $ 1996 Diesel power generation plant
Repetitor stations Kaduna – Abuja, Jos – Makurdi, Akwa Ibom state NITEL/Siemens 1,762,000 $ 1996 Supply, installation & maintenance of 29 solar panel / diesel generator stations
Distribution line 33 kV, Takum, Taraba state Ministry of Power and Steel 740,000 $ 1996 Construction of 25km 33 kV distribution line
Distribution line 33 kV, river crossing, Donga, Bauchi state Ministry of Power and Steel 740,000 $ 1996 Construction of special towers for 33 kV distribution line river crossing
Distribution line 33 kV, river crossing, Tawafa Balewa, Bauchi state Ministry of Power and Steel 740,000 $ 1996 Construction of special towers for 33 kV distribution line river crossing
Power supply to Nigerdock, Lagos Nigerdock 1,800,000 $ 1995 Construction of SS 33/11kV, 11kV underground cable and 11kV SG
Distribution line 33 kV, Micika-Gulag-Madalagi, Adamawa state Ministry of Power and Steel 800,000 $ 1994 Construction of 65km 33 kV distribution line
Distribution line 33 kV, river crossing, Shelleng, Adamawa state Ministry of Power and Steel 100,000 $ 1994 Construction of special towers for 33 kV distribution line river crossing
Power supply to Nigerdock, Lagos Nigerdock 1,700,000 $ 1994 Construction of 33kV SC line from Amuwo to Snake Island and special lagoon crossing towers
Distribution line Oshogbo – Ibadan – reerection and restringing NEPA 1,112,000 $ 1994 Re-erection of 29 collapsed 33kV towers and restringing of 13km 33kV line
LDSE - Lagos Distribution System, 132kV DC TL and 33kV DC DL , Lagos State NEPA 17,000,000 $ 1992 Turn Key project –construction of 120km, 132kV DC transmission line and 40km of 33kV DC distribution line
Kano State Secretariat Kano State Government 82,000,000 $ 1988 Construction of State Government‘s administrative complex with area of 40,000m2
Transmission Line Alagbon – Ikeja, Lagos state NEPA 18,000,000 $ 1984 Construction of 132 kV DC transmission line
Kiri Dam, Yola Irrigation scheme Federal Government 61,000,000 $ 1984 Concrete Water Dam, lake and irrigation system covering 25,000 hectares
Kano river irrigation scheme Federal Government 87,500,000 $ 1983 Irrigation system covering 14,000 hectares
ASCON college Federal Government 68,000,000 $ 1983 Total complex area 5,000 m2
Eye Hospital, Kaduna Federal Government 118,500,000 $ 1980 Total complex area 10,000 m2
Housing settlement, Victoria Island, Lagos Federal Government 9,760,000 $ 1980 High standard condominium of 20 villas with appropriate infrastructure
Flyover interchange, Lagos Federal Government 2,300,000 $ 1978 Traffic roundabout on Badagry expressway
Countrywide electrification program Federal Government 19,500,000 $ 1977 Construction of 1,300km rural electrification lines
International Trade Fair, Lagos Federal Government 223,000,000 $ 1977 12 exhibition pavilions, total area 80,000m2
Electrification of 85 towns Federal Government 18,800,000 $ 1975 Construction of 1,200km rural electrification lines

WORLDWIDE POWER GENERATION, TRANSMISSION AND DISTRIBUTION

 
Project / Location Client Project Value Year of Completion Type of Work / Services
Construction of TL 2 x 400kV Pančevo 2 – Romanian border, Serbia EMS - Serbian Transmission System and Market Operator 27,153,509 $ on going Turn Key
Energy Centre, Minsk, Belarus Gazprom Transgaz Belarus 41,712,000 $ on going Turn Key
Reconstruction of railway station ”Belgrade Center” – Phase I Železnice Srbije a.d. 33,505,992 $ on going Acquisition, Installation & Commissioning
Thermal Power Plant " Nikola Tesla" – Unit A3 reconstruction of electrostatic precipitator, Obrenovac, Serbia EPS-Electrical Power Industry of Serbia /TPP Nikola Tesla 10,075,000 $ 2015 Turn Key
Thermal Power Plant Kostolac B – Unit 2 rehabilitation with reconstruction of electrostatic precipitator, Serbia EPS-Electrical Power Industry of Serbia / Thermal Power Plants and Mines Kostolac LLC 85,800,000 $ 2013 PM, Design, Procurement, installation and commissioning
Thermal Power Plant New Belgrade, - exchanger station on highway no.6,Belgrade, Serbia Public Utility Company “BEOGRADSKE ELEKTRANE” 6,704,230 $ 2012 Acquisition, Installation & Commissioning
New energy supply system of Clinical Center of Niš, Serbia central boiler plant 1CHP (combined heat and power plant); 32 MW Total Capacity; 3 hot water boilers, district heating pump station; central steam boilers; central monitoring system CMS; 8 clinics indoor heating installations; 1,8km district heating pipeline; 18 sub-stations Ministry of Health and Clinical Center Niš 5,700,000 $ 2012 PM, Design, Procurement, installation and commissioning
Double circuit Transmission Line, 400 kV, 100 km, Leskovac 2 – Macedonian border, Serbia Installaciones Inabensa S.A. /EMS (Serbian transmission system and market operator) 8,907,688 $ 2012 PM, Design, Construction
Installation of OPGW Cable with associated equipment on 400 kV, 220 kV, 110 kV and 35 kV Transmission Lines in Serbia EPS – Electrical Power Industry of Serbia 9,750,000 $ 2003-2012 Installed over 2000 km of OPGW cable (5 contracts)
Substation 110/35kV Beograd 1- extension and 2x110kV double cable line, SS Beograd 1 - SS Beograd 28 (3,1 km) EMS - Serbian Transmission System and Market Operator/ABB - Sweden 6,990,000 $ 2010 Turn key
Thermal Power Plant Kolubara A, Unit A5 – reconstruction of electrostatic precipitator and ash handling system, Serbia EPS-Electrical Power Industry of Serbia / TPP Nikola Tesla 19,350,000 $ 2009 Turn key
Double circuit Transmission Line, 400 kV, 40km, Nis – Leskovac, Serbia EMS - Serbian Transmission System and Market Operator 8,972,420 $ 2009 Turn key
New energy supply system of Clinical Center of Serbia - Lot 1 – central boiler plant 1CHP combined heat and power plant 1,8MWe & 1,8MWt, 3 hot water boilers 40MW, district heating pump station, central steam boilers 6t/h, central monitoring system CMS, Belgrade, Serbia Ministry of Health and Clinical Centre of Serbia 10,300,000 $ 2008 PM, Design, supply, construction and maintenance
Thermal Power Plant Nikola Tesla, Unit A4 (308,5 MW) – reconstruction of electrostatic precipitator, Serbia EPS-Electrical Power Industry of Serbia / TPP Nikola Tesla 9,822,488 $ 2007 Turn key
Thermal Power Plant Nikola Tesla, Unit A1 (210 MW) - adaptation and rehabilitation of electrostatic precipitator, Serbia EPS-Electrical Power Industry of Serbia / TPP Nikola Tesla 7,450,000 $ 2006 Turn key
Reconstruction and upgrade of 20 kV distribution network in Ireland (North-east area) ESB, Laing O’Rourke Waterland 14,880,000 $ 2006 Construction

WORLDWIDE BUILDING SERVICES - MEP

 
Project / Location Client Project Value Year of Completion Type of Work / Services
Administrative building – Block 26, New Belgrade, Serbia Blue Centere d.o.o. 15,243,142 $ 2009 Procurement, installation of electrical and mechanical systems, plumbing and automation
Complex Belville - University village, New Belgrade, Serbia Montera/ Blok 67 Associates d.o.o. 14,400,000 $ 2009 Procurement, installation of electrical and mechanical systems, plumbing and automation and TS 10/0,
Shopping Mall, “Delta City”, Block 67, Belgrade, Serbia Delta Holding Co 18,172,534 $ 2007 Mechanical (sanitary and HVAC) and local automatization works
Main Railway Station "Belgrade Centar", Belgrade, Phase I, Serbia BZC, City of Belgrade 20,000,000 $ 2001 Mechanical, Electrical & Plumbing Works
"ETISALAT" Telecommunication and Administration Building Ajman, U.A.E. ETISALAT, U.A.E. 15,000,000 $ 2001 Mechanical, Electrical & Plumbing Works
"Mazaya Center" Commercial and Residential Building Dubai, U.A.E. HH Sheikha Alia Al Maktum, Dubai, U.A.E. 12,000,000 $ 2000 Mechanical, Electrical & Plumbing Works
Three Hospitals - Mandeville, St Ann's Bay and Kingston, Jamaica Rizzani de Eccher S.p.A. 10,000,000 $ 2000 Mechanical, Electrical & Plumbing Works
Bank Association Financial Center of Uzbekistan, Tashkent, Uzbekistan Association of Uzbekistan Banks 4,200,000 $ 2000 Mechanical & Electrical Works
Surgutnetiegaz Bank, Surgut, Russian Federation Surgutnetiegazbank, Surgut 4,350,000 $ 2000 Mechanical, Electrical & Plumbing Works

INDUSTRIAL WASTEWATER TREATMENT PLANTS

 
Project / Location Client Project Value Year of Completion Type of Work / Services
Construction of new Flash Smelter Plant at RTB Bor, Bor, Serbia OUTOTEC 34,826,400 $ 2015 Project Management, Design, procurement and execution of electrical and mechanical works
Construction of new Sulphuric Acid Plant at RTB Bor, Bor, Serbia SNC LAVALIN, Canada 39,400,000 $ 2015 Project Management, Construction works, partial delivery of the equipment and materials, complete er
Pharmaceutical Factory, Tyumen, Russian Federation Tyumen Administration, Russia 25,000,000 $ 2005 Project Management, Design & Build Civil works, MEP & Utilities

WORLDWIDE POTABLE WATER TREATMENT PLANTS

 
Project / Location Client Project Value Year of Completion Type of Work / Services
Potable water Treatment Plant „Bežanijska kosa“, Reconstruction of filtering plant, Belgrade, Serbia Public Utility Enterprise Belgrade water and sewerage 1,495,100 $ 2006 Procurement and Construction of MEP and civil works
7km of potable water distribution piping system – ductile iron pipe material, Kraljevo, Serbia Enterprise for planning and construction of the city of Kraljevo 2,600,000 $ 2005 Turn Key
'Gorina', Leskovac, Raw Water Pipeline, of Potable Water Treatment Plant, Q=3000 m3/h, Serbia Public Utility, Enterprise - Leskovac 2,700,000 $ 2001 Design and Installation

WASTEWATER TREATMENT PLANTS

 
Project / Location Client Project Value Year of Completion Type of Work / Services
Valjevo, Q=1,260 m3/h; Reconstruction & upgrading Serbia Public Utility Enterprise Valjevo 2,500,000 $ 2002/2004 All Works
Kovin, (I phase), Q=360 m3/h, PE 20,000, Serbia Municipality of Kovin 1,800,000 $ 2002 Design and Build
Jagodina, I Phase, Q=2,000 m3/h; PE 89,000, Serbia Municipality of Jagodina 8,900,000 $ 2000 Design and Build